Summary
Replacement of high voltage cable between the Energy Centre and Mullach Sgar as well as Mullach Sgar to Mullach Mor
- Application Validated
- 02/04/2020
- Target Date
- 27/05/2020
- Status
- Granted With Conditions
- Decision Date
- 26/05/2020
Documents
Appeals to Scottish Ministers are processed on their behalf by the Planning and Environmental Appeals Division (DPEA).Appeal forms and guidance notes are available at The Planning System in Scotland on the Scottish Government website. The DPEA publishes all information and correspondence relating to appeals on the DPEA website. We only publish documents when we have been instructed by DPEA to make changes to a designation following an appeal decision. The DPEA search facility enables you to find everything held on the Scottish Government's file which will be considered before a decision is made on an appeal, including any plans, grounds of appeal, our response and any other correspondence. You can also view this information at our principal offices at Longmore House, Salisbury Place, Edinburgh EH9 1SH. Contact Us about this.
Where documents include maps, the use of this data is subject to terms and conditions.
- Type
- Application
- Title
- SM Clearance application
Download
- Type
- Supplementary Information
- Title
- Cable crossing water courses detailed diagram
Download
- Type
- Supplementary Information
- Title
- Plan showing the existing and new HV cable route
Download
- Type
- Supplementary Information
- Title
- Condition Satisfied Letter - Condition 2
Download
- Type
- Supplementary Information
- Title
- Email dated 19 May 2020 - Supplementary Info relating to Application
Download
- Type
- Report on Handling
- Title
- Report on Handling
Download
- Type
- Decision Notice
- Title
- Decision Notice
Download
About Clearance Application
Information in this record is about an application for Scheduled Monument Clearance.
Most works, including repair, on scheduled monuments require Scheduled Monument Consent. However, for departments and agencies of the UK and Scottish Governments undertaking works to monuments in Scotland there is a parallel system known as Scheduled Monument Clearance. This is governed by the same principles and procedures as the Scheduled Monument Consent processes (Scottish Historic Environment Policy section 3.25).
In all cases proposals are assessed by us. Such applications will normally be determined within eight weeks of receipt of the application. Contact Us for application forms and further information.
Applications for Scheduled Monument Clearance and the decisions taken on those applications are published on our online Portal. You can also view this information at our principal offices. Contact Us about this.
Printed: 26/07/2025 09:22